Buying CRA clad or lined pipe without a clear inspection plan is risky. A weak bond, wrong alloy, or missed defect can cause failures in corrosive service that cost far more than the pipe itself. This checklist gives buyers and inspectors a practical framework for verifying clad pipe quality before it leaves the mill.

1. Pre-Production Review

Before manufacturing starts, confirm that the supplier understands and can meet the specification:

  • Purchase order matches the approved drawing and specification
  • Material grades for base pipe and CRA liner are defined
  • Applicable standards are listed (API 5LD, ASME SA-263/264/265, DNV, project-specific)
  • Inspection and test plan (ITP) is approved by buyer or third party
  • Welding procedure specifications (WPS/PQR) are qualified for clad pipe ends
  • Non-destructive testing (NDT) plan is agreed

2. Incoming Material Inspection

Verify that the raw materials match the specification before bonding:

  • Base pipe: Mill test report, heat number, chemical composition, mechanical properties, dimensional check
  • CRA liner: Mill test report, alloy grade verification (PMI), thickness measurement, surface condition
  • Storage: Materials protected from contamination, moisture, and mechanical damage

3. During Production Inspection

Monitor the bonding and fabrication steps that determine final performance:

3.1 Bonding Process Verification

  • Bonding parameters recorded (pressure, temperature, time, deformation)
  • Process controlled within qualified range
  • Visual inspection of bonded interface on sample cuts

3.2 Dimensional Checks

  • Outside diameter and wall thickness at multiple locations
  • Liner thickness measurement (minimum and average)
  • Length, straightness, and out-of-roundness
  • End finish: bevel angle, root face, land width

4. Final Testing and NDE

These tests confirm that the finished pipe meets mechanical and bond integrity requirements:

Test / Inspection Purpose Acceptance Criteria
Ultrasonic Testing (UT)Detect unbonded areas at the CRA-to-base interfaceNo unbonded areas exceeding allowable limits per API 5LD
Shear Bond Strength TestMeasure mechanical bond strength≥ specified minimum (e.g., API 5LD minimum)
Hydrostatic TestVerify pressure integrity of base pipe and bondNo leakage or deformation at test pressure
Flattening TestCheck ductility and bond durabilityNo cracking or delamination at required flattening distance
Bend TestConfirm liner integrity under bendingNo cracks, wrinkles, or separation in CRA layer
Positive Material Identification (PMI)Verify CRA alloy gradeMatches specified grade within tolerance
Visual InspectionCheck surface defects, end preparation, markingFree of cracks, gouges, corrosion; marking legible

5. Documentation Review

Paperwork is as important as the physical pipe. Before shipment, collect:

  • Mill Test Report (MTR) for base pipe and CRA liner
  • Heat numbers and material certificates with full traceability
  • Bond strength test reports
  • Ultrasonic testing reports with defect maps
  • Hydrostatic test certificates
  • NDE inspection reports (UT, RT, MT, PT as applicable)
  • Dimensional inspection report
  • Third-party inspection release note (if applicable)
  • Packing list and shipping documents

6. Pre-Shipment Inspection

  • Random sample visual inspection of finished pipes
  • Verify marking: grade, size, heat number, standard, manufacturer
  • Check end protection caps and sealing
  • Confirm packing method prevents moisture ingress and mechanical damage
  • Review shipping marks and documentation consistency

7. Red Flags That Should Stop Shipment

  • Bond strength values close to or below specification minimum
  • Unbonded areas detected by UT in critical zones
  • CRA alloy grade does not match PMI results
  • Missing or inconsistent heat numbers and traceability records
  • Dimensional deviations outside tolerance
  • Surface defects, corrosion, or contamination on CRA layer
  • Supplier refuses third-party inspection access

8. Conclusion

A structured inspection and quality control process protects buyers from receiving clad pipe that looks correct on paper but fails in service. The most successful projects define the ITP early, witness key tests, and verify documentation traceability before shipment.

ZONX PIPE provides full inspection documentation with every API-5LD clad pipe order, including UT bond inspection reports, hydrostatic test certificates, PMI records, and third-party inspection coordination. Contact us to review a sample quality dossier.

View ZONX Quality Assurance Request Sample Inspection Dossier